Task: Perform Testing Of Back Out Procedures
The final element of release acceptance is the execution of the back out plan.
Relationships
Main Description
It is critical to ensure that the systems can be rolled back to its original state should there be any error during release and deployment. The back out plan must therefore be executed and tested to ascertain if all components of the release can be removed from the environment if the release fails. Tests should not only verify that the back-out scripts are error free but also ensures that the resulting environment can be completely returned to its previous state.

Back out procedures must be updated whenever an issue is identified during this testing. The test results must be recorded and communicated to all stakeholders.